Transformer is Dual Phase ( 120v 120v and one neutral conductor ). ThanksI think you would be safe with about 22, is the transformer just single phase?
Yes, I will be conecting directly to the transformer and it is being use for one house only as there isn't any more house built around yet. ThanksAre you connecting directly to this transformer? If so you will have some work ahead of you, If you time your lighting schedule to use power on peak load times, you could properly get up to 31 lights. (this is running the Transformer at about 140%)
I don't have that info with me as the transformer is on a post, it has a Big 25 on the middle of it. ThanksWhats the model number of the transformer?
Where did you get that info? I believe that you misundestood the concept of the thread. ThanksWow 31 1000watt lights I gotta see this grow
The house is already wired up from that transformer but I am going to do the wire up for the grow rooms, that's why I want to make sure how many 1000 watts lights can be connected to avoid present or future problem with the transformer or the electrical company due to over load or burn it out . Thanks I really appreciate all your helpsAre you going to be doing the wiring? Are you connecting straight to the Transformer or is the place already wired up?
The main concern is not really going to be the actual transformer, but the wiring installed. You need to find the first breaker point after the transformer and figure out what amperage was run there, it could be 100 amp 200 amp maybe 300 amp, single or dual? The actual transformers are very solid and will easily handle 140% of the rated loads, they are much more efficient at there rated loads because of the current saturation around the coils.The house is already wired up from that transformer but I am going to do the wire up for the grow rooms, that's why I want to make sure how many 1000 watts lights can be connected to avoid present or future problem with the transformer or the electrical company due to over load or burn it out . Thanks I really appreciate all your helps
I checked and there is a dual main breaker with a 150 on it, so I have to work on base of 150 amps, thanks to your helps I got a very clear idea. ThanksThe main concern is not really going to be the actual transformer, but the wiring installed. You need to find the first breaker point after the transformer and figure out what amperage was run there, it could be 100 amp 200 amp maybe 300 amp, single or dual? The actual transformers are very solid and will easily handle 140% of the rated loads, they are much more efficient at there rated loads because of the current saturation around the coils.
It wont matter if you have 100kva transformer, you will have to look at what the inbound lines are rated for. At a minimum I would say they did 100 amps per phase to your house which will give you about 10-11 lights per phase safely. I would look at the amperage of the service from the transformer as what to work off of.
In this case, it means that there are two 120v feeds coming off of it. A single phase only has one 120v. Your outlets in your house are single-phase. Dual-phase is where you get 240v across the two hot feeds, or 120v across each feed and the common/neutral wire. This allows you to distribute your gear across the two phases, effectively splitting your current draw in half across each feed.Hi, PICOGRAV
Can you please tell me what would be the different if the transformer is single phase ? Thanks
Sad part is his 150 amp breaker, even at 80% pf is 28.8kVa. You can't look at a residential service as being rated for continuous but intermittent. Duty cy cc le of transformer as well as its efficiency also factor.The main concern is not really going to be the actual transformer, but the wiring installed. You need to find the first breaker point after the transformer and figure out what amperage was run there, it could be 100 amp 200 amp maybe 300 amp, single or dual? The actual transformers are very solid and will easily handle 140% of the rated loads, they are much more efficient at there rated loads because of the current saturation around the coils.
It wont matter if you have 100kva transformer, you will have to look at what the inbound lines are rated for. At a minimum I would say they did 100 amps per phase to your house which will give you about 10-11 lights per phase safely. I would look at the amperage of the service from the transformer as what to work off of.