To get a service upgrade is quite simply going to require that an inspector sign off on the work even if it's done by a homeowner using a permit they pulled themselves. Other than the owner of the residence only a licensed electrician or general contractor can pull the permit. The power company won't stab the new meter until the work is signed off on by a county inspector.
This is what i have now. What im thinking is i can eke out this first harvest and then shut down. Pull the 3 dedicated circuit wires out of the box. Thats what you see on the left with the tape....
Then i hurry up and get the 200 installed. Nobody should need to go any further than the box i pictured. So i can kind of hide it.
Then once theyre finished i can hook back up. Plus im going to need to install a mini split. Probably 24000 btu.
Im barely making it now with a 10k and 5 k window ac's.
The temps spiked but it looks like theyre dropping friday. My ante room is where the passive intake happens and there is a window there so winter will,be my friend.